Minerals and Mining (Licensing) Regulations 2012 (LI 2176)

Regulation 191.

(1)  Within  five days  after  recording  an application  in  the General  Register,  the Mineral Titles Department of Commission shall review the application  to ensure  that
(a) the area applied for is correctly  identified  and the co-ordinates supplied are consistent with the geographic and geometric rules prescribed  in these Regulations;
(b)  the application  was submitted  at least ninety days before the expiration  of the lease;
(c)  the documentation required  is complete  and valid;
(d) the  holder's  activities  under  the  previous  programme of mining  operations  were conducted  satisfactorily;  and
(e)  the applicable  fees have been  duly paid  by the applicant. 
(2) Where an application does  not  comply  with  subregulation (1), the Mineral  Titles Department  of the Commission shall give notice accordingly to the applicant within five days after the review, as set out in Form Three of  the First  Schedule  and  the  applicant  shall  correct  the errors or provide the information  required  within  ten days from the date of the notice.

Subject : Licensing (Mining)  

Procedure to Follow


Submit Your Application
Once you have filled and gathered all the required documents you will have to submit it at the district office.
It takes 5 days to review the application. The next 5 days is for notification of errors.
Submission To Mineral Titles Department (MTD)
10 days after registration, the district office shall submit the application to MTD.
MTD review the application in 10 days and records it in the priority register 
MTD Publishes In The Gazette
15 days after recording, MTD publishes in the gazette, notify chiefs, traditional authorities etc. through the Commission's District Offices. 
Application Dossier
Within
ten (10) days after publication, District Office shall submit application dossier to MTD for appropriate recommendation to Minister
Minister Takes Decision
Once you have completed these steps you are ready to start your business.
You need to renew your license every three (3) years.
Approval / Rejected
21 days notification to applicant and Fees payable if approved.
Reasons are given if rejected. 
Applicable Fees
Within 60 days, applicant pays applicable fees and gives notice of acceptance of the grant to Minister and Commission in writing. 
License
Minister on proof of payment of applicable fees, issues licence to applicant within 30 days after the date of acceptance of the grant....
Responsible Institution


Minerals Commission

36 Second Cantonments Cl, Accra

Relevant Forms to Download

Not Available

Online System

Link Unavailable

Fees/ charges

Not Avaiable