Accra Metropolitan Assembly (Building/ Physical Development) Bye-Laws, 2017

3. Submission of Application and Processing
Inspection of Site
(1)        On receipt of the application form, the Physical Planning Department of the Assembly together with the applicant shall proceed to the site of the proposed development within one week and inspect the area earmarked for the development.
(2)        An applicant shall submit a completed form as specified in the Building Permit Application and Town and Country Planning Form 1 to the Physical Planning Officer of the Assembly.
(3)        The Physical Planning Officer of the Assembly shall notify the applicant on corrections. additional requirements, processing fee and date of inspection of site if necessary
(4)        The Technical Sub-committee of the Assembly shall evaluate the application, visit the site and make recommendation 1o thc Statutory Committee (SPC) within a month of receipt of application.
(5)         The Statutory Planning Committee of the Assembly shall consider the recommendations from the Technical Sub-Committee within nine (9) working days of receipt of thc recommendations  from the Technical Sub-Committee
(6)        The Secretary of the Statutory Planning Committee of the Assembly shall submit approved plan to the Assembly Works Department five (5) working days following approval to issue the building permit.

Subject : Registration of leases and tenencies  

Procedure to Follow


Not Avaiable

Responsible Institution
Relevant Forms to Download

Not Available

Online System

Link Unavailable

Fees/ charges

Not Avaiable